Cab Information D9531 - [ 1 ] [ 2 ] [ 3 ] [ 4 ] [ Photos ] Jobs still outstanding on the cab The majority of the work on the cab is now complete with control systems checked and in place. Wiring from the cab to the power unit and other systems is ongoing. The cab is very much a 'one step forward two steps back' job - doors once rehung/refitted and checked have to be removed again to allow access to complete other jobs such as the air system piping. The new floor although cut and ready will be amongst the final tasks completed. The following jobs still remain:
|